November 26, 2026

How to Quote a CNC Machining Job

#metalshops

17 min read

How to Quote a CNC Machining Job

A good CNC quote is not a number pulled out of the air. It is a short list of costs you can name, added up in the same order every time, with the assumptions written down so the customer can see what they are agreeing to.

Shops that quote well tend to do the same few things in the same sequence. This article walks through that sequence, from the moment an RFQ arrives to the page you send back.

This is about the method. If you are choosing software for it, see our guides to job shop and machine shop quoting software and manufacturing estimating software. The rate you multiply by is covered in how to calculate a shop rate.

The short answer

To quote a CNC machining job, work out the cost of the material (including the stock you cut away), the setup and programming (spread over the quantity), the machine time at the shop rate for each operation, tooling, inspection and any outside processes. Add your margin. Then state the price at two or three quantities, with the drawing revision, your assumptions, the lead time and how long the price holds.

The cost is built in the same order every time:

  • Material, from the stock size and not the finished weight
  • Setup and programming, once per job
  • Cycle time at the shop rate for the machine used
  • Tooling, fixtures and inspection
  • Outside processes, such as finishing or heat treat
  • Margin

If you get the first four right and write down what you assumed, most of the arguments that come later never happen.

Read the RFQ and the print before you price anything

The quote starts with what the customer asked for, not with a price.

Before you open a calculator, pull out the things that change cost:

  • Part number and revision. Quote against a revision, and say which one.
  • Material and condition. Grade, temper or heat-treat state, and whether certifications are needed.
  • Quantity. One number, or several? Is this a one-off, a repeating order or a first run?
  • Tolerances and surface finish. Tight tolerances usually mean slower finishing passes, more inspection, and sometimes a different machine.
  • Features that change the work. Threads, deep pockets, thin walls, tight internal corners, and anything that needs a second setup.
  • Secondary operations. Plating, anodizing, heat treat, painting, inserts, assembly.
  • Delivery. When they need it, and whether it needs to ship partial.

Compare the model with the drawing if you have both. If they disagree, ask before you price. The same goes for anything the print leaves open, like a missing tolerance or material callout. We cover that in the FAQ below.

Size the stock and cost the material

Material cost starts from the stock you buy, not the finished part.

Work out the blank: the bar, plate or billet the part comes from, with the allowance you need to hold it and cut it to size. Then cost that blank at today's price for the material, plus any cut-to-length or minimum-buy charge from your supplier. The part you ship may weigh a fraction of the blank you start from, and the difference is cost the customer is paying for, even though they never see it.

A few things to keep straight:

  • Use a current supplier price. Material prices move, and a price in an old spreadsheet is a guess.
  • Think about how the stock is sold. A part that fits a standard bar size costs less to source than one that forces a larger blank.
  • Certified or special material often comes with a minimum quantity or a longer lead time. Both belong in the quote.
  • If you can machine several parts from one piece of stock, say so in the estimate, but only if you will actually do it.

Do not treat material as a flat percentage of the price. It is a calculated number for this part in this material.

Setup, programming and cycle time

Setup and programming happen once per job. Cycle time happens on every part.

Setup covers loading tools, setting offsets, fixturing, proving the first piece and checking it. A part that needs several operations or orientations has several setups. Count them.

Programming is the time to create or edit the CAM program. A repeat part with an existing program may need almost none. A new part may need a lot.

Cycle time is the machine time to make one part. You can build it from the operations (rough, finish, drill, tap, deburr on the machine), from your CAM software's estimate, from past jobs on similar parts, or from a mix of those. Whichever you use, take the time from your own shop's results where you can. Published feeds and speeds are a starting point, not what your machine did last Tuesday.

Things that quietly add time and are easy to miss:

  • Tight tolerances and fine surface finishes that need extra passes
  • Part handling, flipping and re-fixturing between operations
  • Tool changes, especially on parts that use many tools
  • First-article inspection and in-process checks
  • Deburring and other manual work at the machine

If a feature is unusual and you are not sure how long it will take, say so on the quote as an assumption, or add a clearly labelled line for it. Padding the whole quote to cover one unknown makes you lose jobs you could have won.

Apply the shop rate

Every machine or manual operation is hours times a rate.

Use the rate for the work center that will actually do the work. A five-axis mill, a lathe and a manual bench do not cost the same per hour. If you quote everything at one blended number, the expensive machines look cheaper than they are, and the cheap operations look dearer. Our guide on how to calculate a shop rate covers how to build one rate per work center, and why it should come from billable hours.

Many shops charge setup and programming at their own rate, which may differ from the run rate. Use whichever your shop has defined. What matters is that the rate is written down, and that two estimators looking at the same job use the same one.

Tooling, inspection and outside processes

These are the lines that get left off, then cost money.

  • Tooling and fixtures. Standard tooling wear is often inside the machine rate or charged per hour. Special tools, custom fixtures and soft jaws made for this job are a one-time cost. Charge them as one-time costs, or spread them over the quantity.
  • Inspection. Include the time for first-article inspection, the checks the print calls for, and any CMM or gauge work. If the customer requires a report, price the time to produce it.
  • Outside processes. Get a current price from the vendor, not last year's. Add your handling or coordination cost, and add the vendor's lead time to your own. Outside work often sets the delivery date.
  • Certifications and paperwork. Material certs, certificates of conformance and other documents take time. If the print or the purchase order asks for them, price them.

Packaging and shipping are costs too. Say whether they are in the price or extra.

Quantity breaks, and why the unit price must change

Setup, programming and first-article work are fixed for the job. The more parts you make, the less of that cost each part carries. Quoting one piece and one hundred pieces at the same unit price either loses the big order or loses money on the small one.

The arithmetic is simple. The numbers below are an illustration only, with a round placeholder of one hour of setup at $100 per hour, to show the effect. Use your own setup time and rate.

Quantity Setup cost per part
1 $100 ÷ 1 = $100.00
10 $100 ÷ 10 = $10.00
100 $100 ÷ 100 = $1.00

That is only the setup line. Material, cycle time and the other costs per part stay roughly the same, while the one-time costs spread out. The unit price therefore falls as the quantity goes up, and the customer can see why.

Quote two or three quantities, usually the one the customer asked for and one or two above it. If the customer only asked about one, you can still offer another. Many shops also set a minimum order value so that very small runs cover their handling.

What belongs on the quote you send

A quote is a document the customer may compare against others. Make it easy to say yes to.

Include:

  • Your shop, the customer, the RFQ or quote number, the date and how long the price is valid
  • The part number and revision you quoted
  • Material, condition and finish, and any certifications included
  • The price at each quantity, and the total for each
  • One-time charges, if you show them separately
  • Lead time, counted from the order
  • What is not included, in plain words
  • The assumptions you made: tolerances you are holding, anything the print left open, who supplies the material
  • Terms: payment, shipping and how the customer accepts the quote

The assumptions are the most useful part. They let the customer correct a misunderstanding before you cut metal, instead of after.

Where software helps, and where an estimator still decides

The slow part of quoting is rarely the arithmetic. It is reading the files, working out what the part needs, and re-deciding the same rates and rules each time.

Software can take the reading and the sums off the estimator's desk: measure the part, apply your rates, and produce a breakdown. It does not decide whether a tolerance is realistic on your machine, whether a customer is worth the discount, or whether the lead time is one you can keep. Those stay with the estimator.

MindPal Forge is MindPal's quoting and estimating product for US and Canadian metal fabrication shops and machine shops. It reads the files shops actually receive, including PDF, DXF, STEP, IGES, STL, scans, photos and ZIP packs, and calculates a cost from your machines, materials and rates. The estimator reviews the breakdown, adjusts it and sends the quote.

You can upload a DXF, STEP or PDF to the instant quote demo and see an itemized estimate, with no signup. That demo is a way to judge the reading and the costing, not a substitute for loading your own rates. If you want it set up on your machines, talk to us about a shop pilot.

For how Forge compares with other tools, see the manufacturing quoting software comparison.

Frequently asked questions

How do you quote a CNC machining job?

Read the RFQ and the print, then cost the material (including stock removed), setup and programming, machine time at your shop rate for each operation, tooling, inspection and outside processes. Add margin. State the price at two or three quantities, with the drawing revision, your assumptions, the lead time and how long the quote is valid.

Should I quote per part or per job?

Both. One-time costs such as programming, the first setup and fixtures are paid once per job, so the price per part falls as the quantity rises. Show the unit price and the total at each quantity, so the customer can see the effect and choose.

How do quantity breaks work on a CNC quote?

Setup, programming and first-article work are fixed for the job, so they are divided by the quantity. Material, cycle time and per-part inspection stay close to constant. Two or three quantity breaks show the customer where the unit price drops. A minimum order value covers very small runs.

What should a CNC quote include besides the price?

The part number and revision, the material and finish, the quantities and prices, the lead time counted from the order, how long the price is valid, payment and shipping terms, and what is not included. Also state your assumptions. They are what protects both sides if the print or the order changes.

How long should it take to quote a CNC job?

It depends on the part and on how much of the work is already written down. A repeat part with a known cost can be quick. A new part with several operations, special material or outside processes takes longer. Most delays come from missing information and waiting on outside vendors, not from the arithmetic. Give the customer a date you can meet, and track the time from RFQ received to quote sent on your own work.

What if the drawing is missing a tolerance or material spec?

Ask the customer before you price it, and keep the rest of the quote moving while you wait. If the answer is not available in time, state your assumption on the quote, for example the general tolerance you will hold or the material you priced, so the customer can correct it. Do not hide the uncertainty inside a padded number.