Official budget (from the notice)

$100K – $250K

“Price Range – Between $100,000 and $250,000”

Summary

Amendment 0003 - The purpose of this amendment is to 1) Post updated Schedule of Items (SOI). 2) Extend the RFQ due by date. 3) Clarify the following bridge ratings: Wild Plum Highway Legal loads are 80k lbs and less. Wood Bridge at North Bloomfield not rated. The Due by date has been extended to December 4, 2026 @ 1700 PS. Amendment 0002 - Replies for the Requests For Information are attached. The Site visit log is attached. Amendment 0001 - The purpose of this amendment is to 1) State the correct site visit dates. November 4, 2026 and/or November 5, 2026 at 10:00 AM PT both days. (Only one…